Question & Answer: The table below contains data for the development of a new moutain bike by the Famous Bike…..

Question Help The table below contains data for the development of a new moutain bike by the Famous Bike Company at Phiily. As the project manager, you strive to keep the total project costs to the minimum. The cost information is as follows. Indirect costs are $10,000 per week, and a penalty cost of $8,000 per week will be incurred by your company for every week the project is delayed beyond week 12. Normal Cost Crash Cost Activity Immediate Predecessorls) Normal Time Crash Time (weeks) (weeks) 7,000 3,000 12,000 12,000 8,000 5,000 9,000 14,000 3,000 40,000 22,000 8,000 13,000 16,000 4 D, E 4 1. Draw the project activity-on-node network. 2. How many weeks does the project take to be completed under the normal times? 3. Calculate the total project costs under the normal times (before crashing) 4. Even though the eventual goal is to find the minimum-cost schedule that involves multiple stages of activity crashing, you are only asked to perform the first stage in this complicated task due to time limit of the exam. For this first stage of project crashing, you need to answer the following questions a. What activity(ies) should we crash in the first stage? Why? b. How many weeks should we crash the activity(ies) identified in (a)? Why? c. What are the total project costs after the first stage of crashing?

The table below contains data for the development of a new moutain bike by the Famous Bike Company at Phiily. As the project manager, you strive to keep the total project costs to the minimum. The cost information is as follows. Indirect costs are $10,000 per week, and a penalty cost of $8,000 per week will be incurred by your company for every week the project is delayed beyond week 12. Draw the project activity-on-node network. How many weeks does the project take to be completed under the normal times? Calculate the total project costs under the normal times (before crashing) Even though the eventual goal is to find the minimum-cost schedule that involves multiple stages of activity crashing, you are only asked to perform the first stage in this complicated task due to time limit of the exam. For this first stage of project crashing, you need to answer the following questions a. What activity(ies) should we crash in the first stage? Why? b. How many weeks should we crash the activity(ies) identified in (a)? Why? c. What are the total project costs after the first stage of crashing?

Expert Answer

Answer

Question & Answer: The table below contains data for the development of a new moutain bike by the Famous Bike..... 1Question & Answer: The table below contains data for the development of a new moutain bike by the Famous Bike..... 2

Still stressed from student homework?
Get quality assistance from academic writers!