On the following a. Provide the list of alternative paths b. The optimal path c. How long does the optimal path take? Task Time Immediate predecessor A 3 N/A B 4 N/A C 5 N/A D 5 A,B,C E 8 D F 7 D G 6 D H 12 E,F,G