Write a description explaining to Chase Opportunity what a successful project looks like. In other words, how will Chase know when you have achieved the common goal you set out to achieve? Describe three metrics, or measures, that you will use throughout the project life cycle. Explain how each metric relates to the project.
**below is extra information to help with the questions above:
The Scenario. Chase Opportunity has selected you as the project manager to oversee their latest project – Chase Retail Complex. Chase’s vision is to build four (4) 10,000 square foot buildings (see concept drawing below). Within each building, suite sizes may vary per customer rental agreement (estimating five (5) 2,000 square foot areas per building). Chase has the funds to cover the total project costs and they have already purchased the land for construction. Chase wants to start construction January 2, 2007 and complete the project as soon as possible.
Develop a work breakdown structure (WBS) and a responsibility matrix like those found in your text. You may use MS Word or Excel to develop both of these charts. (A chart and matrix are required.)
The following work activities should be included in your charts. Look them over and determine the best sequence in which they should be accomplished. Some activities (WBS Level 1) may be performed simultaneously whereas others may not. Using your personal knowledge and research, include at least two (2) sub-activities/sub-levels (WBS Level 2) for each activity. Use each of the two (2) names listed under Support Responsibility as a “Primary” for one of your sub-activities/sub-levels and as “Support” for the other sub-activity/sub-level. The WBS and matrix for Activity “Roof” may look something like these examples.
Primary Support
Activity Responsibility Responsibility
Roof Jack Steve, Wally
HVAC Bill Scott, Trevor
Landscaping John Lynn, Beth
Paving Greg Jeff, Pat
Plumbing Max Tyler, Damian
Grading and Site Prep Sal Jim, Joe
Interior Structure Don Keith, Andrea
Foundation Construction Randy Mark, Mike
Exterior Structure Bob Dan, Ken
Electrical Seth Neil, Roy
Part C Prepare a WBS and Gantt Chart in MS Project using the information developed in Part B and the information given. Then explain how much time the overall project is going to take to complete as is.
1. It takes 30 days (standard 8-hour workdays, Monday through Friday) to complete each activity.
2. Construct the WBS and Gantt Chart (in Project) illustrating the construction of each building in sequence. For example, building “A” must be built (completed) before construction on building “B” is started, etc. DO NOT include the Level 2 tasks in your Gantt Chart created in Part B.
Part D Incorporate the following information into your WBS from Part C.
The project manager is paid $30/hour and each primary (P) worker is paid $25/hour while support (S) workers are paid $15/hour.
1. Determine the project’s total labor costs. Explain your results. Submit a copy of your Resource Sheet.
2. When developing the project cost plan, what things should be considered to estimate the total project costs? It may be helpful to contact actual contractors, construction companies, vendors, etc., for the tasks involved in this type of project.
Part E In Part C, your WBS and Gantt Charts were based on each of the buildings being constructed one after the other. We know that building in this manner is a large waste of resources, namely people and time. Revise your original WBS and Gantt charts to reflect better use of your resources. In addition, submit a copy of your new Resource Sheet. Explain the changes you made, why you made them, and how these changes affect your overall project (i.e., costs, project duration, etc.).
Expert Answer
Answer:-
Gantt Chart for Building-A is given in below snapshot similarly for other Buildings can be done:-
While going sequential for 4 buildings and plotting on Gantt Chart all activities one after another, it takes 309 days per building and would require 309×4 = 1236 days but if gone parallel for activities than around 2 years.
Project Cost Calculation:-
Project Cost Plan need to take estimate of material and tool requirement. While resource outsourcing will reduce cost but quality could be compromised as contractor may deliver on time but may not deliver with good quality for his profiteering.
The project labor cost would remain same for all building, hence even going parallel work same timeframe would require and cost for each building would be same