Which of the following is NOT TRUE about the Risk Management Process?
Supports a number of other Technical Management processes. | ||
It is associated with all aspects of the technical effort. | ||
It is a stand-alone program office effort. | ||
It is key to achieve program cost, schedule, and technical performance goals. |
Expert Answer
Risk management process supports many technical management processes, hence option A is true and not the answer.
Almost all aspects of technical efforts are associated with risk management process. Option B is not the answer.
Risk management helps to achieve goals regarding costs, schedule, and performance, hence option D is not the answer.
Option C is the answer.
Risk management is not a stand alone program office effort. It is dependent on many other program office efforts. Like logical solutions, design solutions etc.