Solved: There are two products being produced by a firm with the following bills of material

t Problem 1 1·There are two products being produced by a firm with the following bills of material Q(3) P (2) S(2) Routing Information (all times in hours) Product/ Lot Size WorkOperation Setup Run Time Setup Total Per-Unit 0.8 1.2 Part Center 一hours -perpart Time 20 100 1 of 10.6 40 100 1 of 1 100 200 1of 1 70 300 of 1 50 200 1 of 2 50 300 2 of 2 100 200 of 2 100 300 2 of2 02 1.22 0.4 004 404 029 729 .032 .532 016 816 012 1.212 ,005 905 0.8 1.6 0.8 1.2 0.5 0.5 1.3 0.6 0.9 R. With this information, set up the capacity bills and determine the capacity needed per work center to run the following master schedule: Week Product C Product ID 45 40 20 50 Week 1 Week 2 Week 3 Work CenterCD Fill in the Work Center Load in the table above

There are two products being produced by a firm with the following bills of material: Routing Information (all times in hours) With this information, set up the capacity bills and determine the capacity needed per work center to run the following master schedule: Fill in the Work Center Load in the table above.

Expert Answer

The MRP Schedule: (Assume the items will be produced in same week in which they are ordered)

Item: C
OH = 0
LT = 0
SS = 0
Q = 20
1 2 3
Gross Req. 50 40 45
Scheduled receipts 0 0 0
Projected-on-hand 10 10 5
Net Requirement 50 30 35
Planned order Receipts 60 40 40
Planned order releases 60 40 40
Time/unit on WC #100 0.83 0.83 0.83
Load on WC #100 49.8 33.2 33.2
Time/unit on WC #200 0 0 0
Load on WC #200 0 0 0
Time/unit on WC #300 0 0 0
Load on WC #300 0 0 0
Item: P (1 per item C)
OH = 0
LT = 0
SS = 0
Q = 100
1 2 3
Gross Req. 60 40 40
Scheduled receipts 0 0 0
Projected-on-hand 40 0 60
Net Requirement 60 0 40
Planned order Receipts 100 0 100
Planned order releases 100 0 100
Time/unit on WC #100 0 0 0
Load on WC #100 0 0 0
Time/unit on WC #200 0.404 0.404 0.404
Load on WC #200 40.4 0 40.4
Time/unit on WC #300 0 0 0
Load on WC #300 0 0 0
Item: Q (3 per item C)
OH = 0
LT = 0
SS = 0
Q = 70
1 2 3
Gross Req. 180 120 120
Scheduled receipts 0 0 0
Projected-on-hand 30 50 0
Net Requirement 180 90 70
Planned order Receipts 210 140 70
Planned order releases 210 140 70
Time/unit on WC #100 0 0 0
Load on WC #100 0 0 0
Time/unit on WC #200 0 0 0
Load on WC #200 0 0 0
Time/unit on WC #300 0.729 0.729 0.729
Load on WC #300 153.09 102.06 51.03
Total Load on WC #100 49.8 33.2 33.2
Total Load on WC #200 40.4 0 40.4
Total Load on WC #200 153.09 102.06 51.03
Item: D
OH = 0
LT = 0
SS = 0
Q = 40
1 2 3
Gross Req. 15 20 18
Scheduled receipts 0 0 0
Projected-on-hand 25 5 27
Net Requirement 15 0 13
Planned order Receipts 40 0 40
Planned order releases 40 0 40
Time/unit on WC #100 1.22 1.22 1.22
Load on WC #100 48.8 0 48.8
Time/unit on WC #200 0 0 0
Load on WC #200 0 0 0
Time/unit on WC #300 0 0 0
Load on WC #300 0 0 0
Item: P (2 per item D)
OH = 0
LT = 0
SS = 0
Q = 100
1 2 3
Gross Req. 80 0 80
Scheduled receipts 0 0 0
Projected-on-hand 20 20 40
Net Requirement 80 0 60
Planned order Receipts 100 0 100
Planned order releases 100 0 100
Time/unit on WC #100 0 0 0
Load on WC #100 0 0 0
Time/unit on WC #200 0.404 0.404 0.404
Load on WC #200 40.4 0 40.4
Time/unit on WC #300 0 0 0
Load on WC #300 0 0 0
Item: R (1 per item D)
OH = 0
LT = 0
SS = 0
Q = 50
1 2 3
Gross Req. 40 0 40
Scheduled receipts 0 0 0
Projected-on-hand 10 10 20
Net Requirement 40 0 30
Planned order Receipts 50 0 50
Planned order releases 50 0 50
Time/unit on WC #100 0 0 0
Load on WC #100 0 0 0
Time/unit on WC #200 0.532 0.532 0.532
Load on WC #200 26.6 0 26.6
Time/unit on WC #300 0.816 0.816 0.816
Load on WC #300 40.8 0 40.8
Item: S (2 per item R)
OH = 0
LT = 0
SS = 0
Q = 100
1 2 3
Gross Req. 100 0 100
Scheduled receipts 0 0 0
Projected-on-hand 0 0 0
Net Requirement 100 0 100
Planned order Receipts 100 0 100
Planned order releases 100 0 100
Time/unit on WC #100 0 0 0
Load on WC #100 0 0 0
Time/unit on WC #200 1.212 1.212 1.212
Load on WC #200 121.2 0 121.2
Time/unit on WC #300 0.905 0.905 0.905
Load on WC #300 90.5 0 90.5
Load on WC #100 48.8 0 48.8
Load on WC #200 188.2 0 188.2
Load on WC #300 131.3 0 131.3
Load on WC #100 48.8 0 48.8
Load on WC #200 188.2 0 188.2
Load on WC #300 131.3 0 131.3
Week 1 Week 2 Week 3
C D C D C D
Total Load on WC #100 49.8 48.8 33.2 0 33.2 48.8
Total Load on WC #200 40.4 188.2 0 0 40.4 188.2
Total Load on WC #300 153.09 131.3 102.06 0 51.03 131.3

Don't use plagiarized sources. Get Your Custom Essay on
Solved: There are two products being produced by a firm with the following bills of material