The Acquisition Program Baseline (APB) is a key Input to Systems Engineering activities in Engineering and Manufacturing Development, because it _____.
Defines the “trade space” between the program objectives and thresholds in which trade-offs among cost, schedule and performance goals can be made | ||
Codifies the differences between the user and the program manager with regard to requirements and fielding strategies | ||
Describes the contractor’s past performance | ||
Establishes the repository for the documentation of the three technical baselines |
Expert Answer
Option A.
Becuase it defines the trade space between the program objectives and thresholda in which the trade-offs among cost, schedule and performance goals can be made.
It is a function of Acquisition Program Baseline which helps in performance, costs and scheduling trade offs.