Select all that apply. Which of the following are Technical Planning documents?
Integrated Master Schedule | ||
Integrated Master Plan | ||
Systems Engineering Plan | ||
Capability Development Document |
Expert Answer
Answer
Integrated Master Schedule & Integrated Master Plan
The above options also known as IMS and IMP are critial tools in the form of documnt which helps in planning and scheduling of complex material acquisitions. IMP is an event based documents that document necessary technical and other detais to complete a task. IMS is derived from IMP to form a time based networked schedule to list all taks.