Solved: Please fill in all the values and answer all the questions and please make sure the answers

Please fill in all the values and answer all the questions and please make sure the answers are BIG enough to read. (LLC=Low level code)
LLC Leadtime Lot Sizing Rule Item Skate Lace Box Board 11 Lot for Lot FOO-300 | Foo-400 Lot for Lot FOQ-800 Lot for Lot Lot for Lot |FOQ-1400 2 Wheel Assembly Body Axle Hardware 2| 3 BOM Draw Product Structures Here Boxed Skates Skates (2) Body Axle (2) Hardware (2) Wheel Assembly (2) Laces (2) Box Skateboard Board Wheel Assembly (4) Axle (4) Hardware (4) Complete the transaction files. On a separate sheet, of paper, make a list of any actions that should be taken in the first week.
media%2Fd55%2Fd557d3ad-6ebe-4e81-aa10-75
media%2F8a8%2F8a83234f-564c-44c9-8a68-4a
media%2F507%2F5073a41f-7e74-4641-8cec-3d

LLC Leadtime Lot Sizing Rule Item Skate Lace Box Board 11 Lot for Lot FOO-300 | Foo-400 Lot for Lot FOQ-800 Lot for Lot Lot for Lot |FOQ-1400 2 Wheel Assembly Body Axle Hardware 2| 3 BOM Draw Product Structures Here Boxed Skates Skates (2) Body Axle (2) Hardware (2) Wheel Assembly (2) Laces (2) Box Skateboard Board Wheel Assembly (4) Axle (4) Hardware (4) Complete the transaction files. On a separate sheet, of paper, make a list of any actions that should be taken in the first week.

Expert Answer

MPS 1 2 3 4 5 6 7 8 9
BOXES SKATES 80 80 140
SKATEBOARDS 150 150 200
SKATE LT=1 WEEK L4L SS=0
Gross Requirement 0 160 0 160 0 280 0 0 0
Scheduled Receipts 0 0 0 145 0 280 0 0 0
On Hand 175 175 15 15 0 0 0 0 0 0
Planned Order Release 0 0 145 0 280 0 0 0 0
LACES LT=1 WEEK FOQ 500 SS=50
Gross Requirement 0 160 0 160 0 280 0 0 0
Scheduled Receipts 0 0 0 500 0 0 0 0 0
On Hand 300 300 140 140 480 480 200 200 200 200
Planned Order Release 0 0 500 0 0 0 0 0 0
BOX LT=2 WEEKS FOQ 400 SS=0
Gross Requirement 0 80 0 80 0 140 0 0 0
Scheduled Receipts 0 0 400 0 0 0 0 0 0
On Hand 15 15 0 400 320 320 180 180 180 180
Planned Order Release 400 0 0 0 0 0 0 0 0
BOARD LT=2 WEEKS L4L SS=0
Gross Requirement 0 0 150 0 150 0 200 0 0
Scheduled Receipts 0 0 130 0 150 0 200 0 0
On Hand 20 20 20 0 0 0 0 0 0 0
Planned Order Release 130 0 150 0 200 0 0 0 0
WHEEL ASSEMBLY LT=1 WEEKS FOQ 800 SS=0
Gross Requirement 0 0 890 0 1160 0 800 0 0
Scheduled Receipts 0 0 800 0 800 0 800 0 0
On Hand 450 450 450 360 360 0 0 0 0 0
Planned Order Release 0 800 0 800 0 800 0 0 0
BODY LT=2 WEEKS L4L SS=0
Gross Requirement 0 0 145 0 280 0 0 0 0
Scheduled Receipts 0 0 135 0 280 0 0 0 0
On Hand 10 10 10 0 0 0 0 0 0 0
Planned Order Release 135 0 280 0 0 0 0 0 0
AXLE LT=1 WEEKS L4L SS=35
Gross Requirement 0 0 890 0 1160 0 800 0 0
Scheduled Receipts 0 0 700 0 1160 0 800 0 0
On Hand 225 225 225 35 35 35 35 35 35 35
Planned Order Release 0 700 0 1160 0 800 0 0 0
HARDWARE LT=3 WEEKS FOQ 1400 SS=150
Gross Requirement 0 0 890 0 1160 0 800 0 0
Scheduled Receipts 0 0 0 1400 0 0 1400 0 0
On Hand 700 700 700 0 1400 240 240 840 840 840
Planned Order Release 1400 0 0 1400 0 0 0 0 0
Please note:
the demand in week 2 of BOX and demand in Week 3 of Hardware cannot be fulfilled completely.
Gross requirement (Skates) = MPS (Box Skates) *1
Gross requirement (Laces) = MPS (Box Skates) *2
Gross requirement (Box) = MPS (Box Skates) *1
Gross requirement (Board) = MPS (Sakteboard) *1
Gross requirement (Wheel Assembly) = 2* Planned Order Release (Skates) + 4* MPS (Skateboard)
Gross requirement (Body) = 1* Planned Order Release (Skates)
Gross requirement (Axle) = 2* Planned Order Release (Skates) + 4* MPS (Skateboard)
Gross requirement (Hardware) = 2* Planned Order Release (Skates) + 4* MPS (Skateboard)