LLC Leadtime Lot Sizing Rule Item Skate Lace Box Board 11 Lot for Lot FOO-300 | Foo-400 Lot for Lot FOQ-800 Lot for Lot Lot for Lot |FOQ-1400 2 Wheel Assembly Body Axle Hardware 2| 3 BOM Draw Product Structures Here Boxed Skates Skates (2) Body Axle (2) Hardware (2) Wheel Assembly (2) Laces (2) Box Skateboard Board Wheel Assembly (4) Axle (4) Hardware (4) Complete the transaction files. On a separate sheet, of paper, make a list of any actions that should be taken in the first week.
media%2F05c%2F05c9e57e-e415-4588-81d0-43
media%2Faa2%2Faa2b2e7a-2131-4196-aef7-4e
media%2Fab5%2Fab5a2391-aa38-410b-9dac-85

LLC Leadtime Lot Sizing Rule Item Skate Lace Box Board 11 Lot for Lot FOO-300 | Foo-400 Lot for Lot FOQ-800 Lot for Lot Lot for Lot |FOQ-1400 2 Wheel Assembly Body Axle Hardware 2| 3 BOM Draw Product Structures Here Boxed Skates Skates (2) Body Axle (2) Hardware (2) Wheel Assembly (2) Laces (2) Box Skateboard Board Wheel Assembly (4) Axle (4) Hardware (4) Complete the transaction files. On a separate sheet, of paper, make a list of any actions that should be taken in the first week.

Expert Answer

First, let us admit that the ‘Skateboard’ BOM’s indentation is wrong, the Wheel Assembly, Axle, and Hardware are having LLC=2 and that of the Board is 1, so, the BOM should be as following:

Skateboard

  • Board
    • Wheel Assembly (4)
    • Axle (4)
    • Hardware (4)

Also, note that the FOQ of ‘Lace’ is different in the first table (300) and in the MRP table (500). I have taken it 500.

—————————

Product trees

—————————–

MPS 1 2 3 4 5 6 7 8 9
Boxed Skates 80 80 140
Skateboards 150 150 200
Skate Leadtime = 1 week L4L SS = 0
1 2 3 4 5 6 7 8 9
Gross Req 0 160 0 160 0 280 0 0 0
Sch Rec 0 0 0 0 0 0 0 0 0
On hand 175 175 15 15 0 0 0 0 0 0
POR 0 0 145 0 280 0 0 0 0
Laces Leadtime = 1 week FOQ = 500 SS = 50
1 2 3 4 5 6 7 8 9
Gross Req 0 160 0 160 0 280 0 0 0
Sch Rec 0 0 0 0 0 0 0 0 0
On hand 300 300 140 140 480 480 200 200 200 200
POR 0 0 500 0 0 0 0 0 0
Box Leadtime = 2 weeks FOQ = 400 SS = 0
1 2 3 4 5 6 7 8 9
Gross Req 0 80 0 80 0 140 0 0 0
Sch Rec 0 0 0 0 0 0 0 0 0
On hand 15 15 335 335 255 255 115 115 115 115
POR 400 0 0 0 0 0 0 0 0 0
Board Leadtime = 2 weeks L4L SS = 0
1 2 3 4 5 6 7 8 9
Gross Req 0 0 150 0 150 0 200 0 0
Sch Rec 0 0 0 0 0 0 0 0 0
On hand 20 20 20 0 0 0 0 0 0 0
POR 130 0 150 0 200 0 0 0 0
Wheel Assy Leadtime = 1 week FOQ = 800 SS = 0
1 2 3 4 5 6 7 8 9
Gross Req 520 160 600 160 800 280 0 0 0
Sch Rec 0 0 0 0 0 0 0 0 0
On hand 450 730 570 770 610 610 330 330 330 330
POR 800 0 800 0 800 0 0 0 0 0
Body Leadtime = 2 weeks L4L SS = 0
1 2 3 4 5 6 7 8 9
Gross Req 0 80 0 80 0 140 0 0 0
Sch Rec 0 0 0 0 0 0 0 0 0
On hand 10 10 0 0 0 0 0 0 0 0
POR 70 0 80 0 140 0 0 0 0 0
Axle Leadtime = 1 week L4L SS = 35
1 2 3 4 5 6 7 8 9
Gross Req 520 0 890 0 1360 0 0 0 0
Sch Rec
On hand 225 35 35 35 35 35 35 35 35 35
Net Req 330 0 890 0 1360 0 0 0 0
POR 330 0 890 0 1360 0 0 0 0
POR 330 0 890 0 1360 0 0 0 0 0
Hardware Leadtime = 3 weeks FOQ=1400 SS = 150
1 2 3 4 5 6 7 8 9
Gross Req 520 0 890 0 1360 0 0 0 0
Sch Rec 0 0 0 0 0 0 0 0 0
On hand 700 180 180 690 690 730 730 730 730 730
POR 1400 0 1400 0 0 0 0 0 0 0