You receive an order of 200 salads in 4 hours. In addition you have 3 salad stations that all have a part in making the salad.
Station 1= 20 seconds
Station 2= 30 seconds
Station 3=35 seconds
Calculate the labor content in second
Calculate the takt time
Calculate the Tarket Takt manpower
Expert Answer
The labor content calculation is shown below:
Don't use plagiarized sources. Get Your Custom Essay on
Question & Answer: You receive an order of 200 salads in 4 hours. In addition you have 3 salad stations…..
GET AN ESSAY WRITTEN FOR YOU FROM AS LOW AS $13/PAGE
20+30+35= 85
The labor content is the sum of all process steps that is the sum of Station 1= 20 seconds, Station 2= 30 seconds and Station 3=35 seconds and the labor content is 85.
The takt time calculation is shown below:
85/4=21.2
The net available time is divide with the customer demand and that value is known as takt time, that is net available time in 3 station is 85 and that is divided by customer demand on 4 hours and the total is 21.2
Target Takt Manpower:
To calculate the Target Takt Manpower we should know the value of takt time and that is 21.2. The manpower can be allocated accurate.