What is the probability of completing this project within 16 days? Using excel NORMDIST function to find the correct probability for your computed z-score.
https://newconnect.mheducation.com/flow/connect.html 4: Project Managment Saved You received partial credit in the previous attempt. Che Problem 4-10 The following represents a project that should be scheduled using CPM TIMES (DAYS) IMMEDIATE ACTIVITY PREDECESSORS amb 3 4 11 c, D D, E F, G

https://newconnect.mheducation.com/flow/connect.html 4: Project Managment Saved You received partial credit in the previous attempt. Che Problem 4-10 The following represents a project that should be scheduled using CPM TIMES (DAYS) IMMEDIATE ACTIVITY PREDECESSORS amb 3 4 11 c, D D, E F, G