-What is the forecast for week 16 using exponential smoothing with α = 0.4? Assume that the forecast for week 1 was 55. The final forecast for period 16 should be rounded off to the nearest whole number.

-What is the forecast for week 16 using exponential smoothing with α = 0.6?

Assume that the forecast for week 1 was 55. The final forecast for period 16 should be rounded off to the nearest whole number.

-What is the mean square error for the forecast with α = 0.4 as of week 15? Do not use the squared error for week one in your MSE calculation.

-What is the mean square error for the forecast with α = 0.6 as of week 15? Do not use week one in your calculations.

-What is the period 15 tracking signal for the forecast with α = 0.4?

-What is the period 15 tracking signal for the forecast with α = 0.6?

-Assume that the control limits for the tracking signal are ±4. What can be concluded about the quality of the forecasts using α = 0.40 or α = 0.60?

-What is the forecast for period 16 using the three-period moving average? The final forecast for period 16 should be rounded off to the nearest whole number.

The number of flowers sold at The Blossom Shop on Fridays is shown in the table below Week Demand Week 6 7 8 9 10 Demand Week 50 57 60 58 63 50 50 58 73 Demand 69 52 67 58 70 2 3 4 12 13 15 Round off all calculations to two decimal places. Maintaining two decimal places is required for all calculations

Expert Answer

Answer

a) For alpha = 0.4, Forecast for week 16 = 64

b) For alpha = 0.6, Forecast = 66

c) MSE for alpha = 0.4 is 935.80/(14-1) = 71.98

d) MSE for alpha = 0.6 is 1045.78/(14-1) = 80.44