Question & Answer: value 10.00 points JK Concert Promotions 12,000 EL Home Builders Actual indirect materials costs Actual indirect labor costs…..

value 10.00 points JK Concert Promotions 12,000 EL Home Builders Actual indirect materials costs Actual indirect labor costs Other overhead costs Overhead applied $ 56,000 17,000 96,200 $ 6,500 46,500 49,000 106,800 Record the journal entry to close over-or underapplied factory overhead to Cost of Goods Sold for each of the independent cases above. (Omit the $ sign in your response.) General Journal JK Concert Promotions (Click to select) (Click to select) EL Home Builders (Click to select) Click to select Hints References Hint #1Question & Answer: value 10.00 points JK Concert Promotions 12,000 EL Home Builders Actual indirect materials costs Actual indirect labor costs..... 1Question & Answer: value 10.00 points JK Concert Promotions 12,000 EL Home Builders Actual indirect materials costs Actual indirect labor costs..... 2

value 10.00 points JK Concert Promotions 12,000 EL Home Builders Actual indirect materials costs Actual indirect labor costs Other overhead costs Overhead applied $ 56,000 17,000 96,200 $ 6,500 46,500 49,000 106,800 Record the journal entry to close over-or underapplied factory overhead to Cost of Goods Sold for each of the independent cases above. (Omit the “$” sign in your response.) General Journal JK Concert Promotions (Click to select) (Click to select) EL Home Builders (Click to select) Click to select Hints References Hint #1

Expert Answer

 

As multiple questions have been asked, only one cn be answered at a time.
JK Concert Promotions:
Factory overhead 11200 =96200-(12000+56000+17000)
         Cost of goods sold 11200
EL Home Builders:
Factory overhead 4800 =106800-(6500+46500+49000)
         Cost of goods sold 4800