The following materials standards have been established for a particular product: Standard quantity per unit of output 4.2 meters Standard price $ 18.40 per meter The following data pertain to operations concerning the product for the last month: Actual materials purchased 7,200 meters Actual cost of materials purchased $ 138,600 Actual materials used in production 6,700 meters Actual output 1,550 units

What is the materials price variance for the month?

Don't use plagiarized sources. Get Your Custom Essay on
Question & Answer: The following materials standards have been established for a particular product: Standard quantity per unit of output 4.2 meters Standard pr…..
GET AN ESSAY WRITTEN FOR YOU FROM AS LOW AS $13/PAGE
Order Essay

$3,658 U

$7,700 U

$11,770 U

$6,120 U

Expert Answer

 

STANDARD COST FOR MATERIAL
Std. Quantity Per Unit Standard Price Standard Cost Per Unit
4.2 18.4 77.28
Actual Rate per unit = Actual Cost / Actual Material Purchased
Actual Rate per unit = $138,600 / 7200
Actual Rate per unit = $ 19.25 Per Meter
Material price Variance = (Standard Price – Actual Price) * Actual Quantity
Standard Prcie = $18.40 Per Meter
Actual Prcie = $19.25 Per Meter
Actual Quantity Purchased = 7200 Meters
Material price Variance = ($18.40 – $19.25) * 7200 Meters
Material price Variance =   $ 0.85 * 7200 Meters
Material price Variance =   $ 6120 (Unfavorable)
Answer = Option 4= Material Price variance = $ 6120 (Unfavorable)