Expert Answer

 

1.Direct Material. Material requisition slips

Direct labor. Time tickets

Manufacturing overhead. Predetermined overhead rate

2. Predetermined Overhead Rate = Manufacturing overhead / Direct labor = 1947 / 1570 = 124%

3. Total cost of the completed job = Direct material + Direct labor + Manufacturing overhead

=4,765 + 1,570 + 1,947 = 8,282

Unit cost of completed job = Total cost / Total units = 8,282 /2,390 = 3.4 per unit