Question & Answer: Sox Engineering designs and constructs air conditioning and heating​ (HVAC) systems…..

Sox Engineering designs and constructs air conditioning and heating​ (HVAC) systems for hospitals and clinics. Currently the​ company’s staff is overloaded with design work. There is a major design project due in 9 weeks. The penalty for completing the design late is ​$14,000 per​ week, since any delay will cause the facility to open later than​ anticipated, and cost the client significant revenue. If the company uses its inside engineers to complete the​ design, it will have to pay them overtime for all work. Sox has estimated that it will cost ​$10,000 per week​ (wages and​ overhead), including late​ weeks, to have company engineers complete the design. Sox is also considering having an outside engineering firm do the design. A bid of ​$85,000 has been received for the completed design. Yet another option for completing the design is to conduct a joint design by having a third engineering company complete all electromechanical components of the design at a cost of ​$52,000. Sox would then complete the rest of the design and control systems at an estimated cost of ​$30,000. Sox has estimated the following probabilities of completing the project within various time frames when using each of the three options. Those estimates are shown in the following​ table:

Probability of Completing the Design
Option On Time One Week Late Two Weeks Late Three Weeks Late
Internal Engineers 0.4 0.5 0.1
External Engineers 0.2 0.5 0.2 0.1
Joint Design 0.2 0.2 0.4 0.2

The expected monetary value using inside engineers to complete the design is ​$______​(Enter your response as an integer.​)

Don't use plagiarized sources. Get Your Custom Essay on
Question & Answer: Sox Engineering designs and constructs air conditioning and heating​ (HVAC) systems…..
GET AN ESSAY WRITTEN FOR YOU FROM AS LOW AS $13/PAGE
Order Essay

The expected monetary value using outside engineers to complete the design is ​$______​(Enter your response as an integer.​)

The expected monetary value of conducting a joint design is ​$______​(Enter your response as an integer.​)

Expert Answer

Internal Engineers Option:

Wages per week = $10,000

Late Penalty cost = $14,000 beyond 9 weeks

For Internal Engineers the payoff or cost for the project as per week schedule is as follows:

Events Cost Structure Payoff Probability of completion Expected Payoff
On time (in 9 weeks) Wages and OH for 9 days 9 x 10,000

= 90,000

0.4 (0.4)(90,000)

= 36,000

One week late (in 10 weeks) Wages and OH for 10 days + penalty for 1 week delay (10)(10,000) + (1)(14,000)

= 114,000

0.5 (0.5)(114,000)

= 57,000

Two weeks late (in 11 weeks) Wages and OH for 11 days + penalty for 2 week delay (11)(10,000) + (2)(14,000)

= 138,000

0.1 (0.1)(138,000)

= 13,800

Three weeks late (in 12 weeks) Wages and OH for 12 days + penalty for 3 week delay (12)(10,000) + (3)(14,000)

= 162,000

0 (0)(139,000)

= 0

Expected Monetary Value 106,800

EMV using Inside Engineers to complete design = $106,800

External Engineers Option:

Bid Cost = $85,000

Late Penalty cost = $14,000 beyond 9 weeks

For Internal Engineers the payoff or cost for the project as per week schedule is as follows:

Events Cost Structure Payoff Probability of completion Expected Payoff
On time (in 9 weeks) Bid Cost 85,000 0.2 (0.2)(85,000)

= 17,000

One week late (in 10 weeks) Bid Cost + penalty for 1 week delay 85,000 + (1)(14,000)

= 99,000

0.5 (0.5)(99,000)

= 49,500

Two weeks late (in 11 weeks) Bid Cost + penalty for 2 week delay 85,000 + (2)(14,000)

= 113,000

0.2 (0.2)(113,000)

= 22,600

Three weeks late (in 12 weeks) Bid Cost + penalty for 3 week delay 85,000 + (3)(14,000)

= 127,000

0.1 (0.1)(127,000)

= 12,700

Expected Monetary Value 101,800

EMV using External Engineers to complete design = $101,800

Joint Design Option:

Total Cost of project = $52,000 + $30,000 = $82,000

Late Penalty cost = $14,000 beyond 9 weeks

For Internal Engineers the payoff or cost for the project as per week schedule is as follows:

Events Cost Structure Payoff Probability of completion Expected Payoff
On time (in 9 weeks) Total Joint Cost 82,000 0.2 (0.2)(82,000)

= 16,400

One week late (in 10 weeks) Total Joint Cost + penalty for 1 week delay 82,000 + (1)(14,000)

= 96,000

0.2 (0.2)(96,000)

= 19,200

Two weeks late (in 11 weeks) Total Joint Cost + penalty for 2 week delay 82,000 + (2)(14,000)

= 110,000

0.4 (0.4)(110,000)

= 44,000

Three weeks late (in 12 weeks) Total Joint Cost + penalty for 3 week delay 82,000 + (3)(14,000)

= 124,000

0.2 (0.2)(124,000)

= 24,800

Expected Monetary Value 104,400

EMV using Joint Design option to complete design = $104,400