Question & Answer: Required information The Foundational 15 [LO7-1, LO7-3, LO7-4) The following information applies to the questions displayed below] Hickory Company manufactures two pro…..

Use photo below to answer all part of questions
Required information The Foundational 15 [LO7-1, LO7-3, LO7-4) The following information applies to the questions displayed below] Hickory Company manufactures two products-14,000 units of Product Y and 6,000 units of Product Z. The company uses a plantwide overhead rate based on direct labor-hours. It is considering implementing an activity-based costing (ABC) system that allocates all $586,500 of its manufacturing overhead to four cost pools. The following additional information is available for the company as a whole and for Products Y and Z EstimatedR overhead Expected Activity Cost Poolilll Activity Measure Machining Machine setups Product design General factory CostlActivity $ 195,000 10,000 MHs Machine-hours Number ot setups7 500 Number of products 79,000 Direct labor-hours$ 245,000 12,000 DLHS 2 products Activity Measure lProduct xProduct 2 Machine-hours Number of setups Number of products 6,5003,500 100 50 5004,500 Foundational 7-9 くPrev 91011 15of 18 Next >
9) media%2Fe20%2Fe209482c-a6f0-465e-8802-8010) media%2F764%2F76440059-72c4-4d80-a00b-36media%2Fe6d%2Fe6d31e24-d3fb-436f-833e-c7
12)
media%2Fbfb%2Fbfb26a02-b46e-4a24-935d-4413) media%2F2c7%2F2c781ebb-6d61-4a62-a46c-b314 media%2F638%2F6389d33c-c869-472b-9ae8-cc
15)
media%2F502%2F502cb293-c16a-4000-8322-8d

Required information The Foundational 15 [LO7-1, LO7-3, LO7-4) The following information applies to the questions displayed below] Hickory Company manufactures two products-14,000 units of Product Y and 6,000 units of Product Z. The company uses a plantwide overhead rate based on direct labor-hours. It is considering implementing an activity-based costing (ABC) system that allocates all $586,500 of its manufacturing overhead to four cost pools. The following additional information is available for the company as a whole and for Products Y and Z EstimatedR overhead Expected Activity Cost Poolilll Activity Measure Machining Machine setups Product design General factory CostlActivity $ 195,000 10,000 MHs Machine-hours Number ot setups7 500 Number of products 79,000 Direct labor-hours$ 245,000 12,000 DLHS 2 products Activity Measure lProduct xProduct 2 Machine-hours Number of setups Number of products 6,5003,500 100 50 5004,500 Foundational 7-9 くPrev 91011 15of 18 Next >

Expert Answer

 

Before solving the questions we need find out OH (overhead ) rate per each of the activity pools. These rate are calculated by dividing the pool amount by activity frequency. For example 195000/10000 = 19.5

Activity cost pool Amount Activity OH per Act
Machining 195000 10000 19.5
Machine setups 67500 150 450
Product design 79000 2 39500
General factory 245000 12000 20.4166667

Question – 7.9

Total Manufacturing Overhead cost assigned to Product Y
Activity pool Act used OH per act OH assigned
Machining 6500 19.5 126750
Machine setups 50 450 22500
Product design 1 39500 39500
General factory 7500 20.416667 153125
           Total OH assigned to Product – Y 341875

Question 7.10

Total Manufacturing Overhead cost assigned to Product Z
Activity pool Act used OH per act OH assigned
Machining 3500 19.5 68250
Machine setups 100 450 45000
Product design 1 39500 39500
General factory 4500 20.416667 91875
           Total OH assigned to Product – Y 244625

Question – 7.11

Plant wide overhead recovery rate = Total OH / Total Lab Hrs
                                             = 586500 / 12000            =     48.875
%
Product – Y 7500 * 48.875 = 366562.5 62.5
Product – Z 4500* 48.875 = 219937.5 37.5

Note % are calculated as ……366562.5 / 586500 * 100 = 62.5% and 219937.5 / 586500 * 100 = 37.5 %

7.12 USING ABC SYSTEM
Machine cost Amount %
Product – Y 126750 65
Product – Z 68250 35
Total 195000 100
7.13 Using ABC SYSTEM % of machine setup cost
Amount      %
Product – Y 22500 33.33
Product – Z 45000 66.67
Total 67500
7.14   Using ABC SYSTEM % of product design cost
Amount      %
Product – Y 39500 50
Product – Z 39500 50
Total 79000
7.15    Using ABC system % of general factory cost
Amount     %
Product – Y 153125 62.5
Product – Z 91875 37.5
Total 245000
Still stressed from student homework?
Get quality assistance from academic writers!