Qu12. CH 12, 14 Qulz This Question: 1 pt Submit Quiz 3 of 4 This Quiz: 4 pts possible The demand for subassembly S is 140 units in week 7. Each unit of Srequires 2 units of T and 1 unit of U Each unit of T requires 2 units of V. 1 unit of W, and2 units of X. Finaly, each unit of U requires 1 unit of Y and 2 units of Z One firm manufactures all tems. It takes 2 weeks to make S. 1 week to make T, 2 weeks to make U, 2 weeks to make V. 3 weeks to make W. 1 week to make X, 2 weeks to make Y, and 1 week to make 2 Click the icon to view the product Click the icon to view the on-hand inventory Suppose that in addition to 140 units of S, there is also a demand for 20 units of u, which is a component of S. The 20 units of U are needed for maintenance purposes. These units are needed in week 6 Modify the net material requirem Construct a new net material requirements plan (enter your responses as wnole nombers) plan to reflect this change Gross req n hand Net req 120 Order release 120 Enter your answer in each of the answer boxes
Answer