ONLY QUESTIONS E, F AND G!!!!
Problem 8-27A Computing standard cost and analyzing variances Spiro Company manufactures molded candles that are finished by hand. The company developed the following standards for a new line of drip candles Amount of direct materials per candle Price of direct materials per pound Quantity of labor per unit Price of direct labor per hour Total budgeted fixed overhead 1.6 pounds $1.50 1 hour $20/hour $390,000 CHECK FIGURES During 2017, Spiro planned to produce 30,000 drip candles. Production lagged behind expectations, and it actually produced only 24,000 drip candles. At year-end, direct materials purchased and used amounted to 40,000 pounds at a unit price of $1.35 per pound. Direct labor costs were actually $18.75 per hour and 26,400 actual hours were worked to produce the drip candles. Overhead for the year actually amounted to S330,000. Overhead is applied to products using a predetermined overhead rate based on estimated units e. Usage variance for direct materials: $2,400 U f. Fixed cost volume variance: $78,000U Required Page 385
Expert Answer
e | ||||||||
1 | Direct Material Variance | |||||||
Price variance=(SR-AR)*AQ | 6000 | Favourable | ||||||
Usage variance=(SQ-AQ)*SR | -2400 | Unfavourable | ||||||
Total direct material variance | 3600 | Favourable | ||||||
2 | Direct labour variance | |||||||
Rate variance=(SR-AR)*AQ | 33000 | Favourable | ||||||
Efficiency variance=(SQ-AQ)*SR | -48000 | Unfavourable | ||||||
Total direct labour variance | -15000 | Unfavourable | ||||||
Material Variance | ||||||||
Actual Cost | Actual Rate | Actual Quantity | Standard Cost | Standard Rate | Standard Quantity | |||
54000 | 1.35 | 40000 | 57600 | 1.5 | 38400 | |||
(40000*1.35) | (38400*1.5) | (24000*1.6) | ||||||
Labour Var | ||||||||
Actual Cost | Actual Rate | Actual Quantity | Standard Cost | Standard Rate | Standard Quantity | |||
495000 | 18.75 | 26400 | 480000 | 20 | 24000 | |||
(26400*18.75) | (24000*20) | (24000*1) | ||||||
Usage variance should be investigated for both material and labour since these are unfavourable. | ||||||||
Possible cause of usage variance is inefficient utilisation of resources. | ||||||||
f | Fixed Cost Spending | |||||||
Fixed Overhead Budget Variance =Budgeted Fixed Overhead – Actual Fixed Overhead | ||||||||
=390000-330000 | ||||||||
60000 | Favourable | |||||||
Fixed Overhead Volume Variance | ||||||||
Fixed Overhead Application Rate =Budgeted Fixed Cost / Budgeted Production | ||||||||
=390000/30000 | ||||||||
13 | per unit | |||||||
Applied fixed overhead=Overhead application rate*Actual no. of units produced=13*24000= | 312000 | |||||||
Budgeted Fixed Overhead | 390000 | |||||||
Fixed OH Volume Var=Applied OH-Budgeted OH | ||||||||
=312000-390000 | ||||||||
-78000 | Unfavourable | |||||||
Since less units are produced than budgeted fixed volume variance is unfavourable. | ||||||||
g | ||||||||
When difference in per unit cost is seen it is very small in cents. But when it is mutiplied with quantity it become a significant amount. | ||||||||
Moreover the ineffecient use of resources further contribute to the vraiances. | ||||||||