Question & Answer: Problem 139 The board of directors of Ogle Construction Company is meeting to choose between the co…..

Problem 139 The board of directors of Ogle Construction Company is meeting to choose between the completed-contract method and the percentage-of-completion method of accounting for long-term contracts in the companys financial statements. You have been engaged to assist Ogles controller in the preparation of a presentation to be given at the board meeting. The controller provides you with the following information: 1. Ogle commenced doing business on January 1, 2018 2. Construction activities for the year ended December 31, 2018, were as follows: Contract Costs Estimated Total Contract Billings Through Cash Collections Incurred Through Additional Costs to 12/31/18 Through 12/31/18 12/31/18 Complete Contracts 95,000 434,000 Project Price 494,000 714,000 472,000 197,000 444,000 $2,321,000 $334,000 204,000 469,000 94,000 394,000 $1,495,000 $304,000 204,000 384,000 62,000 394,000 $1,348,000 418,000 186,000 344,000 117,000 314,000 $1,379,000 91,000 78,500 $698,500 3. Each contract is with a different customer 4. Any work remaining to be done on the contracts is expected to be completed in 2019 Compute the amount of income (or loss) before selling, general, and administrative expenses for the year ended December 31, 2018, which would be reported under: (1) The completed-contract method (2) The percentage-of-completion method (based on estimated costs)Question & Answer: Problem 139 The board of directors of Ogle Construction Company is meeting to choose between the co..... 1

Problem 139 The board of directors of Ogle Construction Company is meeting to choose between the completed-contract method and the percentage-of-completion method of accounting for long-term contracts in the company’s financial statements. You have been engaged to assist Ogle’s controller in the preparation of a presentation to be given at the board meeting. The controller provides you with the following information: 1. Ogle commenced doing business on January 1, 2018 2. Construction activities for the year ended December 31, 2018, were as follows: Contract Costs Estimated Total Contract Billings Through Cash Collections Incurred Through Additional Costs to 12/31/18 Through 12/31/18 12/31/18 Complete Contracts 95,000 434,000 Project Price 494,000 714,000 472,000 197,000 444,000 $2,321,000 $334,000 204,000 469,000 94,000 394,000 $1,495,000 $304,000 204,000 384,000 62,000 394,000 $1,348,000 418,000 186,000 344,000 117,000 314,000 $1,379,000 91,000 78,500 $698,500 3. Each contract is with a different customer 4. Any work remaining to be done on the contracts is expected to be completed in 2019 Compute the amount of income (or loss) before selling, general, and administrative expenses for the year ended December 31, 2018, which would be reported under: (1) The completed-contract method (2) The percentage-of-completion method (based on estimated costs)

Expert Answer

 

Don't use plagiarized sources. Get Your Custom Essay on
Question & Answer: Problem 139 The board of directors of Ogle Construction Company is meeting to choose between the co…..
GET AN ESSAY WRITTEN FOR YOU FROM AS LOW AS $13/PAGE
Order Essay

SOLUTION

1.

Projects A B C D E
Contract price (1) 494,000 714,000 472,000 197,000 444,000
Contract costs incurred 418,000 186,000 344,000 117,000 314,000
Additional Costs to complete 95,000 434,000 0 91,000 78,500
Total cost (2) 513,000 620,000 344,000 208,000 392,500
Total gross profit or (loss) (1-2) (19,000) 94,000 128,000 (11,000) 51,500

a-The amount reported as income (loss) under the completed-contract method for 2018 is:

Project A (19,000)
Project B 0
Project C 128,000
Project D (11,000)
Project E 0
98,000

b-The amount reported as income (loss) under the percentage-of-completion method for 2018 is:

Project A (19,000)
Project B (94,000*186,000/620,000) 28,200
Project C 128,000
Project D (11,000)
Project E (51,500*314,000/392,500) 41,200
167,400

2.

Accounts title and Explanation Debit ($) Credit ($)
Construction in Process 28,200
Construction Expenses 186,000
  Revenue from Long-term Contracts 214,200

3.

Particulars Amount ($)
Billings 94,000
Cash collections 62,000
Accounts receivable 32,000
Billings on Construction in Process 100,000
Costs incurred 117,000
Loss reported (11,000)
Construction in process 106,000

4.

The account balances would be the same.

Still stressed from student homework?
Get quality assistance from academic writers!