Question & Answer: On February 1, 2018, Arrow Construction Company entered into a three-year construction contract to build a brid…..

On February 1, 2018, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,025,000. During 2018, costs of $2,010,000 were incurred, with estimated costs of $4,010,000 yet to be incurred. Billings of $2,512,000 were sent, and cash collected was $2,260,000. In 2019, costs incurred were $2,512,000 with remaining costs estimated to be $3,615,000. 2019 billings were $2,762,000, and $2,485.000 cash was collected. The project was completed in 2020 after additional costs of $3,810,000 were incurred. The companys fiscal year-end is December 31. This project does not qualify for revenue recognition over time Requlred 1. Calculate the amount of revenue and gross profit or loss to be recognized in each of the three years. 2a. Prepare journal entries for 2018 to record the transactions described (credit various accounts for construction costs incurred). 2b. Prepare journal entries for 2019 to record the transactions described (credit various accounts for construction costs incurred). 3a. Prepare a partial balance sheet to show the presentation of the project as of December 31, 2018. 3b. Prepare a partial balance sheet to show the presentation of the project as of December 31, 2019 Complete this question by entering your answers in the tabs below Req 1 Req 2A Req 2B Req 3A Req 3B Calculate the amount of revenue and gross profit or loss to be recognized in each of the three years. (Loss amounts should be indicated with a minus sign.) Revenue Gross profit (loss) Year 2018 2019 Tots < Req 1 Req 2A >Please help me by showing the work so I can understand. Thanks

On February 1, 2018, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,025,000. During 2018, costs of $2,010,000 were incurred, with estimated costs of $4,010,000 yet to be incurred. Billings of $2,512,000 were sent, and cash collected was $2,260,000. In 2019, costs incurred were $2,512,000 with remaining costs estimated to be $3,615,000. 2019 billings were $2,762,000, and $2,485.000 cash was collected. The project was completed in 2020 after additional costs of $3,810,000 were incurred. The company’s fiscal year-end is December 31. This project does not qualify for revenue recognition over time Requlred 1. Calculate the amount of revenue and gross profit or loss to be recognized in each of the three years. 2a. Prepare journal entries for 2018 to record the transactions described (credit “various accounts” for construction costs incurred). 2b. Prepare journal entries for 2019 to record the transactions described (credit “various accounts” for construction costs incurred). 3a. Prepare a partial balance sheet to show the presentation of the project as of December 31, 2018. 3b. Prepare a partial balance sheet to show the presentation of the project as of December 31, 2019 Complete this question by entering your answers in the tabs below Req 1 Req 2A Req 2B Req 3A Req 3B Calculate the amount of revenue and gross profit or loss to be recognized in each of the three years. (Loss amounts should be indicated with a minus sign.) Revenue Gross profit (loss) Year 2018 2019 Tots

Expert Answer

 

Don't use plagiarized sources. Get Your Custom Essay on
Question & Answer: On February 1, 2018, Arrow Construction Company entered into a three-year construction contract to build a brid…..
GET AN ESSAY WRITTEN FOR YOU FROM AS LOW AS $13/PAGE
Order Essay
Answer 1.
Completed Contract Method
2018 2019 2020
Revenue                         –                          –          8,025,000
Less: Cost                         –                          –          8,332,000
Gross Profit                         –                          –           (307,000)
Answer 2(a) & 2(b)
Journal Entry
Date Particulars Dr. Amt. Cr.Amt.
2018
a. Work In Progress                        Dr.          2,010,000
   To Accounts Payable / Cash          2,010,000
b. Accounts Receivables               Dr.          2,512,000
   To Billings          2,512,000
c. Cash                                                 Dr.          2,260,000
   To Accounts Receivables          2,260,000
2019
a. Work In Progress                        Dr.          2,512,000
   To Accounts Payable / Cash          2,512,000
b. Accounts Receivables               Dr.          2,762,000
   To Billings          2,762,000
c. Cash                                                 Dr.          2,485,000
   To Accounts Receivables          2,485,000
Answer 3(a) & 3(b)
Balance Sheet (Partial)
2018 2019
Accounts Receivables              252,000              529,000
Work in Progress          2,010,000          4,522,000