Question & Answer: Kelle Carpet and Trim installs carpet in commercial offices. Peter Kelle has been very…..

Kelle Carpet and Trim installs carpet in commercial offices. Peter Kelle has been very concerned with the amount of time it took to complete several recent jobs. Some of his workers are very unreliable. A list of activities and their optimistic completion time, the most likely completion time, and the pessimistic completion time (all in days) for a new contract are given in the following table Time (days) Immediate Time (days) Immediate Ativity a m b Predecessor(s)Activity a bPredecessor(s) A, E 10 12 13 13 15 17 13 H, I B, D A, E This exercise contains only parts b, c, and d b) Activities on the critical path for the project are

Kelle Carpet and Trim installs carpet in commercial offices. Peter Kelle has been very concerned with the amount of time it took to complete several recent jobs. Some of his workers are very unreliable. A list of activities and their optimistic completion time, the most likely completion time, and the pessimistic completion time (all in days) for a new contract are given in the following table: This exercise contains only parts b, c, and d. b) Activities on the critical path for the project are

Expert Answer

Answer

Still stressed from student homework?
Get quality assistance from academic writers!