Question & Answer: In the following table the activities with their precedence sequence and expected time (days) are listed for a…..

In the following table the activities with their p

In the following table the activities with their precedence sequence and expected time (days) are listed for a project on which Carl Betterton’s construction company is working: Carl’s team should be able to complete the project in days.

Expert Answer

 The connected paths and time setimates are given in the attached image below:

Thus the paths are:

1. ABDG 2. ABEH 3. ACFH

Path duration for ABDG = 7+4+6+6 = 23

Path duration for ABEH = 7+4+4+8 = 23

Path duration for ACFH = 7+6+4+8 = 25

Thus, ACFH is the critical path and the project will be completed in 25 days.

Still stressed from student homework?
Get quality assistance from academic writers!