Question & Answer: fit nearly any small car. The company has a standard cost system in use for all of its products. According to the…..

Marvel Parts, Inc., manufactures auto accessories. One of the company’s products is a set of seat covers that can be adjusted to fit nearly any small car. The company has a standard cost system in use for all of its products. According to the standards that have been set for the seat covers, the factory should work 1,030 hours each month to produce 2,060 sets of covers. The standard costs associated with this level of production are:

 

Total Per Set
of Covers
  Direct materials $ 39,140 $ 19.00
  Direct labor $ 9,270 4.50
  Variable manufacturing overhead
(based on direct labor-hours)
$ 3,502 1.70
$ 25.20

 

During August, the factory worked only 640 direct labor-hours and produced 1,600 sets of covers. The following actual costs were recorded during the month:
Total Per Set
of Covers
  Direct materials (5,500 yards) $ 29,920 $ 18.70
  Direct labor $ 7,520 4.70
  Variable manufacturing overhead $ 4,000 2.50
$ 25.90

 

At standard, each set of covers should require 2.50 yards of material. All of the materials purchased during the month were used in production.

 

Required:
1. Compute the materials price and quantity variances for August. (Input all amounts as positive values. Indicate the effect of each variance by selecting “F” for favorable, “U” for unfavorable, and “None” for no effect (i.e, zero variance).)

 

2. Compute the labor rate and efficiency variances for August. (Input all amounts as positive values. Indicate the effect of each variance by selecting “F” for favorable, “U” for unfavorable, and “None” for no effect (i.e, zero variance).)

 

3. Compute the variable overhead rate and efficiency variances for August. (Input all amounts as positive values. Indicate the effect of each variance by selecting “F” for favorable, “U” for unfavorable, and “None” for no effect (i.e, zero variance).)

 

Expert Answer

 

Data for Resource Variance
Budgeted Standard Actual
Quantity/Hrs Rate Amount Quantity/Hrs Rate Amount Quantity/Hrs Rate Amount
Material(Yard) 5150 7.6 39140 4000 7.6 30400 5500 5.44 29920
Labour 1030 9 9270 800 9 7200 640 11.75 7520
V. Overhead 1030 3.4 3502 800 3.4 2720 640 6.25 4000
Total 51912 40320 41440
1. Computation of Variances
a) Material Price Variance = (Standard Price – Actual Price ) Actual Quantity
                                              = (7.6-5.44) * 5500
                                              =11880/- Favourable
Material Quantity Variance = (Standard quantity – Actual Quantity ) Standard Price
                                                       = (4000 – 5500 )7.6
                                                        = 11400 Unfavorable
b) Labour Rate Variance = (Standard Rate – Actual Rate) Actual Hrs Worked
                                       = (9-11.75)640
                                       = 1760 Unfavorable
Labour Efficiency Variance = (Standard Hrs. – Actual Hrs) Standard Rate
                                                = (800-640 )9
                                                 =1440 Favorable
c) Variable Overhead(OH) Rate Variance = (Standard Rate – Actual Rate ) Actual Machine Hrs Worked
                                                                     =(3.4-6.25)640
                                                                     =1824 Unfavorable
Variable OH Efficiency Variance = (Standard hrs. – Actual Hrs) Standard Rate
                                                         = (800-640)3.4
                                                         =544 Favourable
Still stressed from student homework?
Get quality assistance from academic writers!