Engel Appliances has developed a new European-style convection oven that will be made on an assembly line. The schedule requires 120 ovens in an 8-hour day The assembly includes seven tasks. The table below indicates the performance time and the sequence. requirements for each task. The cycle time per oven for this assembly operation is: 4.0 minutes/oven. The precedence diagram is shown below. It shows that the actual number of workstations is 5 along with the specific tasks assigned to the workstation. WS = workstation.