Question & Answer: Development of Version 2.0 of a particular accounting software product is being…..

Development of Version 2.0 of a particular accounting software product is being considered by Jose​ Noguera’s technology firm in Baton Rouge. The activities necessary for the completion of this project are listed in the following​ table:

Activity normal time(weeks) crash time(weeks) normal cost total cost with crashing immediate predeccesors
a 4 2 2100 2800
b 2 1 2200 3000
c 3 3 600 600
d 8 4 2300 2580 A
e 6 3 800 2250 B
f 3 2 3000 4400 c
g 4 2 1500 2000 D,E

what is the project completion date ?

what is the total cost required for completing this project on normal time?

if you wish to reduce the time required to complete this project by 1 week, which activity should be crashed and how much will this increase the total cost?

what is the max time that can be crashed? how much would costs increase?