Information about the activities of a project is provided below.

Activity Predecessor Normal time (weeks) Crash Time (weeks) Normal Cost Crash Cost
a none 6 5 $9,000 $10,000
b none 8 6 $3,000 $4,000
c none 4 3 $5,000 $6,200
d A,B 5 3 $9,000 $12,000
e C 8 5 $10,000 $16,000

Information about the activities of a project is provided below. Which activity or activities should be crashed to reduce the project duration to 12 weeks?

Don't use plagiarized sources. Get Your Custom Essay on
Answered! Information about the activities of a project is provided below….
GET AN ESSAY WRITTEN FOR YOU FROM AS LOW AS $13/PAGE
Order Essay

Expert Answer

 Solution : Activity C should be crashed to reduce the project duration to 12 weeks.