Information about the activities of a project is provided below.
Activity | Predecessor | Normal time (weeks) | Crash Time (weeks) | Normal Cost | Crash Cost |
a | none | 6 | 5 | $9,000 | $10,000 |
b | none | 8 | 6 | $3,000 | $4,000 |
c | none | 4 | 3 | $5,000 | $6,200 |
d | A,B | 5 | 3 | $9,000 | $12,000 |
e | C | 8 | 5 | $10,000 | $16,000 |
Information about the activities of a project is provided below. Which activity or activities should be crashed to reduce the project duration to 12 weeks?
Expert Answer
Solution : Activity C should be crashed to reduce the project duration to 12 weeks.