Answered! Information about the activities of a project is provided below….

Information about the activities of a project is provided below.

Activity Predecessor Normal time (weeks) Crash Time (weeks) Normal Cost Crash Cost
a none 6 5 $9,000 $10,000
b none 8 6 $3,000 $4,000
c none 4 3 $5,000 $6,200
d A,B 5 3 $9,000 $12,000
e C 8 5 $10,000 $16,000

Information about the activities of a project is provided below. Which activity or activities should be crashed to reduce the project duration to 12 weeks?

Expert Answer

 Solution : Activity C should be crashed to reduce the project duration to 12 weeks.

Still stressed from student homework?
Get quality assistance from academic writers!