Information about the activities of a project is provided below.
Activity | Predecessor | Normal time (weeks) | Crash Time (weeks) | Normal Cost | Crash Cost |
a | none | 6 | 5 | $9,000 | $10,000 |
b | none | 8 | 6 | $3,000 | $4,000 |
c | none | 4 | 3 | $5,000 | $6,200 |
d | A,B | 5 | 3 | $9,000 | $12,000 |
e | C | 8 | 5 | $10,000 | $16,000 |
Information about the activities of a project is provided below. Which activity or activities should be crashed to reduce the project duration to 12 weeks?
Don't use plagiarized sources. Get Your Custom Essay on
Answered! Information about the activities of a project is provided below….
GET AN ESSAY WRITTEN FOR YOU FROM AS LOW AS $13/PAGE
Expert Answer
Solution : Activity C should be crashed to reduce the project duration to 12 weeks.