In the following table the activities with their precedence sequence and expected time (days) are listed for a project on which Carl Betterton’s construction company is working: Carl’s team should be able to complete the project in days.
Expert Answer
The connected paths and time setimates are given in the attached image below:
Thus the paths are:
Don't use plagiarized sources. Get Your Custom Essay on
Answered! In the following table the activities with their precedence sequence and expected time (days) are listed for a…
GET AN ESSAY WRITTEN FOR YOU FROM AS LOW AS $13/PAGE
1. ABDG 2. ABEH 3. ACFH
Path duration for ABDG = 7+4+6+6 = 23
Path duration for ABEH = 7+4+4+8 = 23
Path duration for ACFH = 7+6+4+8 = 25
Thus, ACFH is the critical path and the project will be completed in 25 days.