Here is a partial work breakdown structure for a wedding.
Hint: Start with the last activity (wedding reception) and work your way back to the staart of the project. Build logical sequence tasks by asking the following question. In order to have or do this, what must be accomplished before this?
1. Enter the information into Microsoft Project using Manual Scheduling Mode for the entry of items, and indent tasks to create summary tasks.
2. Use GanttChart Tools to Format the View and make the outline numbers visible in the Task Name.
1. Wedding project
1.1 decide date
1.2 marriage license
1.3 ceremony
1.3.1 rent church
1.3.2 florist
1.3.3 create/print programs
1.3.4 hire photographer
1.3.5 wedding ceremony
1.4 guests
1.4.1 develop guest list
1.4.2 order invitations
1.4.3 address and mail invitations
1.4.4 track rsvps
1.5 reception
1.5.1 reserve reception hall
1.5.2 food and beverage
1.5.2.1 choose caterer
1.5.2.2 decide on menu
1.5.2.3 make final order
1.5.3 hire band
1.5.4 decorate reception hall
1.5.5 wedding reception