Answered! Activity Predecessor Optimistic Pessemistic Expected Variance A   2 6 4 0.44…

Activity Predecessor Optimistic Pessemistic Expected Variance
A 2 6 4 0.44
B 1 9 3 1.78
C A 2 6 4 0.44
D B 5 17 9 4
E C 3 11 5 1.78
a)      How many weeks should John Black allow for completion of the project if he is comfortable with only a 2.5% chance of being late?

Expert Answer

 

a) Number of weeks that John Black should allow for completion of the project with only 2.5% chance of being late (i.e. 97.5% chance of completing within that time) = 16.2 weeks (in the above sceenshot, pls read weeks in place of days)